Show or hide done tasks on the Timeline
Hide finished work from the Timeline, Gantt and Network views without changing any date.
This applies where your workspace has the Timeline's Network view. Where it does not, tasks work as they did before.
- On a project's Timeline tab, open Filter and switch Show done tasks off.
- Done means a task in a done column, the same rule the board uses.
- The Network still works out every date with the done tasks in it, then hides them. A note says how many are hidden, and a faint dotted line keeps the order readable where a hidden done task sat between two others.
- Navalo remembers your choice for each project. It starts on.
Still stuck? Open a support ticket and we'll help you out - tracked right inside Navalo.